Projects funded by Infrastructure Canada, in every province.

Key figures

20,520projects31 programs · 13 regions · approved from 2002 to 2026
39.4%finished after the published planned date6,841 of 17,350 carrying both dates · median delay 110 dayshow it's calculated

Finished after the planned date — where the number comes from

The calculation
6,841 projects finished after the planned date ÷ 17,350 projects carrying both dates = 39.4%
What goes in
Projects that publish both a construction end date and a planned end date. The median delay, in the base, only covers projects finished after the planned date, in calendar days. The planned date is the one the source publishes today, not necessarily the original.
Source
INFC — funded infrastructure projects · Open Government Licence – Canada (OGL-Canada-2.0) · data up to date as of January 19, 2026 · link to this detail
40.0%median federal share of eligible costmedian contribution $321,829 · quartiles $80,000 and $1,169,647how it's calculated

Median federal share of eligible cost — where the number comes from

The calculation
For each project: the federal contribution ÷ the eligible cost. The median of these shares: 40.0%.
What goes in
Projects whose eligible cost is above zero and that publish a contribution. The tile's base — the median federal contribution and its quartiles — covers all projects that publish a contribution.
Source
INFC — funded infrastructure projects · Open Government Licence – Canada (OGL-Canada-2.0) · data up to date as of January 19, 2026 · link to this detail
2,357without an actual end date1,478 with a planned end still ahead · 878 whose planned end has passed · 1 with no published planned end

By region

By region
RegionProjectsLateMedian contributionFederal share
Ontario7,62437.6%2,538 of 6,743$174,14440.0%
Quebec3,52440.5%1,244 of 3,074$461,30140.0%
British Columbia1,89835.9%534 of 1,486$670,50443.0%
Saskatchewan1,46425.2%309 of 1,225$215,95633.3%
Newfoundland and Labrador1,43248.2%585 of 1,213$193,96740.0%
Alberta1,13535.3%331 of 937$805,40340.7%
Nova Scotia88039.5%270 of 683$450,00040.0%
New Brunswick80851.2%329 of 642$480,00049.8%
Manitoba75247.8%276 of 577$384,03240.0%
Prince Edward Island45864.4%260 of 404$328,60940.0%
how it's calculated — By region

By region — where the number comes from

What goes in
“Late”: the actual end is after the planned end published by the source, which may have been revised. Each percentage has its base written beside it. Medians, never sums: the largest contribution would crush any average. A funded project is not a tender: it has no closing date, no bidder, no method. The contracts that follow are published elsewhere — often by a province or a city.
Source
INFC — funded infrastructure projects · Open Government Licence – Canada (OGL-Canada-2.0) · data up to date as of January 19, 2026 · link to this detail

Infrastructure Canada, Government of Canada Open Data · aggregates of January 19, 2026

By program

By program
Program ENProjectsMedian contribution
Infrastructure Stimulus Fund ISF4,029$273,171
Clean Water and Wastewater Fund CWWF2,320$200,000
COVID-19 Resilience Stream CVRIS2,230$324,113
Municipal Rural Infrastructure Fund MRIF1,925$125,000
Green Infrastructure Stream GIS1,654$694,980
Public Transit Infrastructure Fund PTIF1,141$169,621
Building Canada Fund - Communities Component CC950$464,941
Provincial-Territorial Infrastructure Component - Small Communities Fund SCF950$416,245
Community, Culture & Recreation Infrastructure Stream CCRIS807$437,960
Rural & Northern Infrastructure Stream RNIS743$711,396
how it's calculated — By program

By program — where the number comes from

What goes in
A program covers an era: its projects were approved in those years, and its lateness rate is not comparable to that of a program still open, many of whose projects have no actual end.
Breakdown
By program
Program ENApprovedLate
National Recreational Trails Program2009 – 2015n/ano project carries both dates
Public Transit Infrastructure Stream2018 – 202524.3%50 of 206
Building Canada Fund - Communities Component Top Up2009 – 201036.1%193 of 534
Active Transportation Fund2022 – 202479.1%234 of 296
Green and Inclusive Community Buildings Program2021 – 202672.2%57 of 79
Provincial-Territorial Infrastructure Component - National and Regional Projects2014 – 202552.9%120 of 227
Permanent Public Transit Program2022 – 202560.8%87 of 143
Building Canada Fund - Major Infrastructure Component2008 – 201745.2%70 of 155
Disaster Mitigation and Adaptation Fund2018 – 202442.9%6 of 14
Canada Strategic Infrastructure Fund2002 – 201431.5%17 of 54
Source
INFC — funded infrastructure projects · Open Government Licence – Canada (OGL-Canada-2.0) · data up to date as of January 19, 2026 · link to this detail

Infrastructure Canada, Government of Canada Open Data · aggregates of January 19, 2026